Hydrogen Strategic Project H2 Triangle

We are investors in the Strategic project H2 Triangle encompassing local hydrogen economy construction, R&D activities focused on hydrogen technologies and manufacturing and assembling halls, which will be rented to hydrogen & fuel cell technology suppliers. The project will be realized in the Strategic Industrial Zone Triangle.

Project developer: FOR H2ENERGY s.r.o.
Time schedule: 2022 – 2025

 

COMPLEX HYDROGEN PROJECT H2 TRIANGLE CONSISTS OF:

  • Local hydrogen economy construction
  • R&D activities
  • Manufacturing and assembling halls for hydrogen technology suppliers

 

H2 TRIANGLE TECHNICAL PARAMETERS

  • PV power output – 4 MWp
  • Electrolyser capacity – 4 MW (630 t of H2/year)
  • Refueling stations – Filling pressures – 700 bar (light-duty vehicles) and 350 bar (heavy-duty vehicles)
  • Fuel cell power – approx. 75 kW  

H2 Triangle feasibility study was developed with the support of Usti region and the project is being prepared for its realization. A reservation agreement for the land purchase was signed.  

 

TIME SCHEDULE FOR THE NEXT STEPS

  • 01/2023 – 12/2023
    • Site and building permit
  • 01/2024 – 12/2025
    • Construction of hydrogen production unit, R&D center and refueling station
    • Assembling hall no.1 construction and installation on of photovoltaic panels on the roofs
    • Installation of photovoltaic panels on remaining grounds
  • 01/2026 – 05/2026
    • Test run

 

PROJECT COVERS THE WHOLE GREEN HYDROGEN VALUE CHAIN

R&D | Manufacturing and assembling halls | Photovoltaic plant | Electrolytical production of green hydrogen | Compression | Storage | Refueling station | Fuel cell

Inside the complex of the Strategic Industrial Zone Triangle will be installed a photovoltaic power plant, water electrolysis for the green hydrogen production, compressors and both low-pressure and high-pressure tanks for storage and distribution.


The green hydrogen production unit will utilize renewable electricity generated by the solar panels. A fuel cell will be a part of the hydrogen economy as well for the purpose of the conversion of the green hydrogen back to renewable electricity for the investors in the Strategic Industrial Zone Triangle as well as its surrounding areas. Last but not least, a hydrogen refueling station will be built in the complex as well. 


The project considers also a construction of R&D center and manufacturing / assembling halls, which will represent a base for suppliers of necessary components for electrolyzers, compressors, low-pressure and high-pressure hydrogen tanks, hydrogen refueling stations and fuel cells.

 

PROJECT PARTNERS

  • Usti region
    • Lands, Strategic Industrial Zone Triangle services
  • UJEP
    • R&D
  • Fund HYDROGEN2
    • Financing
  • CHEMINVEST s.r.o.
    • Engineering, R&D
  • Investors in the Strategic Industrial Zone Triangle
    • Green hydrogen and electricity offtake